Every week, on site
The construction team photographs the building every week. 44 visits since Jan 5, 2026, newest first; tap a photo to see it large.
October 20263 visits
Oct 19, 2026
Closets and wood doors go in, the elevator rails are set, the rooftop takes shape
Oct 12, 2026
Kitchen cabinets go in, work continues on the rooftop
Oct 5, 2026
Joint compound on the drywall, the rooftop structures go up
September 20264 visits
Sep 28, 2026
Drywall taped in the units, the rooftop pool takes shape
Sep 21, 2026
Corridor floor pour and drywall
Sep 14, 2026
Windows and sliding doors installed
Sep 7, 2026
Drywall and ceiling installations
August 20265 visits
Aug 31, 2026
Drywall partitions going up
Aug 24, 2026
Bathroom vanities and closet framing
Aug 17, 2026
The banner on the facade, tiled floors inside
Aug 10, 2026
Rooftop works, electrical panels and floor tile
Aug 4, 2026
Facade painting from the ropes
July 20264 visits
Jul 28, 2026
The rooftop pool from above, walls in plaster
Jul 21, 2026
Facade glazing and rooftop walls
Jul 14, 2026
Rooftop block walls, floors being prepared
Jul 7, 2026
Terraces and the view from the upper floors
June 20265 visits
Jun 30, 2026
Electrical boxes and wiring in the units
Jun 23, 2026
First sliding door installed
Jun 16, 2026
Terrace walls and ceiling installations
Jun 9, 2026
Floors and walls prepared inside
Jun 2, 2026
Pool shell walls, poured into the night
May 20264 visits
May 28, 2026
Rooftop pool pour
May 26, 2026
From the air, conduits on the floors
May 19, 2026
Interior walls and ceilings in progress
May 12, 2026
Rebar for the rooftop pool, interior finishes
April 20264 visits
Apr 28, 2026
Ground works for services, plumbing risers inside
Apr 20, 2026
Facade scaffolding and rooftop works
Apr 14, 2026
Roof pour, kitchens being fitted
Apr 6, 2026
Kitchen cabinets in, electrical fittings
March 20265 visits
Mar 30, 2026
Rooftop structures, interiors in finishes
Mar 24, 2026
Street front glazed, rooftop walls in formwork
Mar 17, 2026
Rooftop parapets take shape
Mar 9, 2026
Rooftop slab pour with the pump
Mar 3, 2026
Rooftop rebar and interior plaster
February 20265 visits
Feb 27, 2026
Rooftop slab pour
Feb 24, 2026
White facade on the lower floors
Feb 17, 2026
Roof slab cast, interiors in drywall
Feb 10, 2026
Rebar for the roof slab, drywall ceilings inside
Feb 3, 2026
Facade finishes begin
January 20265 visits
Jan 27, 2026
Wall formwork on the roof, interiors in plaster
Jan 20, 2026
Walls rising on the roof level
Jan 13, 2026
Slab rebar on the top level, first plaster inside
Jan 10, 2026
Columns and formwork for the top levels
Jan 5, 2026
The frame reaches the upper floors
A selection of 264 photographs from the developer's weekly site visits. Dates are the day of the visit.